top of page
103-1039115_iphone-users-click-below-home-button-png-icon_edited.png
103-1039115_iphone-users-click-below-home-button-png-icon_edited.png
AU Logo.png
AU Logo.png

AMERICAN CONSTRUCTION NEWS

October 21, 2026 at 2:29:50 PM

Intel’s Ohio One: What a Longer Construction Timeline Means for Builders

Hurricane in City

A major chip-factory project is underway in Licking County, but workforce planning must reflect Intel’s revised schedule.

Summary
• Intel says it plans to invest more than $28 billion in two Ohio chip factories.
• In its February 2025 update, Intel targeted completion of Mod 1 in 2030 and Mod 2 in 2031.
• A March 2026 building-trades report put the site workforce near 1,000 and described a planned increase of roughly 600; those were dated projections.
• Long timelines create opportunities for specialty contractors but require careful scheduling.

Sources: https://www.intel.com/content/www/us/en/newsroom/news/corporate/ohio-one-construction-timeline-update.html ; https://columbusconstruction.org/dorsey-hager-talks-data-center-pushback-bluegrass-power-station-and-eli-lilly-on-awf-union-podcast/

The problem.

Intel’s Ohio One campus in New Albany, Licking County, is one of the largest private construction projects in the state’s history. Intel has said it plans to invest more than $28 billion in two leading-edge chip factories, and the site has been under construction since 2022. For contractors, suppliers and tradespeople across Central Ohio, a project of that size naturally creates expectations: more bid packages, more hiring, more years of steady work.

The problem is that expectations and schedules do not always move together. In February 2025, Intel announced that it was slowing the pace of construction to align the project with business needs and market demand. The company now plans to complete construction of the first fab, Mod 1, in 2030 and begin operations between 2030 and 2031. The second fab, Mod 2, is expected to be finished in 2031 and begin operations in 2032. Intel also said it would keep the flexibility to accelerate work if customer demand warrants.

That creates a planning challenge. A subcontractor that hires a crew, buys equipment or turns down other work in anticipation of an Intel package can be exposed if that package arrives later than expected. A training program that promises graduates immediate placement on the site can disappoint students if the work is phased differently. Even local governments and businesses that plan housing, roads or services around the project need to know when demand will actually arrive.

Workforce figures add to the confusion. In March 2026, Dorsey Hager of the Columbus/Central Ohio Building and Construction Trades Council reported that close to 1,000 building trades members were working on site and that Bechtel planned to add roughly 600 more over the following 60 to 90 days as weather improved and exterior work increased. Those were useful figures at the time, but they describe a single moment and a forecast. They should not be repeated months later as if they were a current, confirmed headcount.

The real issue for Ohio’s construction industry is not whether Ohio One matters. It clearly does. The issue is how to participate in a long, phased megaproject without making business decisions based on outdated numbers or headlines.

A deeper understanding.

A semiconductor fab is not built like a warehouse or an office building. The project moves through distinct stages, and each stage needs different trades, skills and suppliers. Intel reported that it reached its ‘go vertical’ milestone after completing the fab’s basement level, with work on the above-ground structure underway. Later stages of a project like this typically involve building enclosure, extensive mechanical and electrical systems, highly controlled interior environments and commissioning before production can start.

That sequence matters because labor demand is not evenly distributed. A concrete or steel contractor may be busiest in one period, while electrical, piping and commissioning specialists may see their heaviest demand later. When an owner slows the overall pace, it can affect each of those phases differently. A slower schedule may extend the life of the project, but it can also spread work over more years and reduce the intensity of hiring in any one season.

The Ohio One campus is also part of a wider ecosystem. In his March 2026 remarks, Hager connected the Intel project to data centers, behind-the-meter power plants and supplier companies expected to arrive in the region over the following year to year and a half. He also noted that the project continues to track toward Intel’s goal of producing chips by 2031. That broader activity can create real opportunity, but each related project has its own owner, financing, permits and procurement path. A supplier facility or roadway improvement is not automatically awarded, funded or scheduled because Intel is building nearby.

Precision manufacturing work also raises the bar for quality and documentation. Cleanliness requirements, tight tolerances, material traceability and careful coordination among structural, mechanical, electrical and process systems all matter more than on a typical commercial job. Firms that want to participate need more than available labor. They need supervisors who understand the documentation, safety and quality procedures that complex facilities demand.

Finally, Intel’s timeline is driven by global business conditions, not just local construction capacity. The company has been clear that it wants to align production with market demand and manage capital responsibly. That means contractors should expect continued schedule updates and should treat every published date as a planning target that may change.

The Solution.

The most practical way to approach Ohio One is to treat it as a series of construction phases rather than a single hiring wave. Start by mapping your company’s services to the stages of the project. A sitework firm, a structural steel erector, a mechanical contractor and a commissioning specialist will each experience the project on a different timeline. Once you know where your work falls, follow Intel’s official updates, the prime contractor’s procurement announcements and formal bid invitations to identify when your scope is actually likely to be released. Planning around published milestones and confirmed bid packages is far safer than planning around a projected peak headcount.

Build staffing plans from awarded work, not from headlines. A rolling three- to six-month labor forecast tied to signed contracts helps a company avoid hiring ahead of its backlog. If an Ohio One package looks promising but is not yet awarded, consider temporary measures such as verified subcontracting relationships or shared crews rather than permanent expansion. It is also wise to keep other work in the pipeline. Pharmaceutical plants, hospitals, data centers and utility projects can use many of the same skills, giving a firm somewhere to deploy crews if a semiconductor package is delayed.

Invest in capabilities that last beyond one owner. Semiconductor projects demand strong quality control, documented inspections, material traceability and disciplined change management. Training supervisors in these areas, documenting relevant past experience and building written procedures can help a firm qualify for Ohio One packages, and those same strengths make the firm more competitive on other complex projects. Workforce programs can follow the same principle by teaching precision mechanical, electrical and controls skills that transfer to many industries.

Local governments and utilities also have a role. Publishing clear, regularly updated schedules for related roads, water and power work helps contractors and residents plan. Those agencies should distinguish their own projects from Intel’s packages so the public understands which improvements are funded, approved and scheduled.

Key actions:
• Confirm current schedules and scopes with Intel or the responsible prime contractor before committing crews.
• Treat dated workforce figures as historical context, not a current hiring promise.

average rating is 4 out of 5, based on 150 votes, Ratings
bottom of page